Commit 50386fbc authored by Andrew Morton's avatar Andrew Morton Committed by Linus Torvalds

[PATCH] sched: fix imbalance calculations

From: Nick Piggin <nickpiggin@yahoo.com.au>

Imbalance calculations were not right.  This would cause unneeded migration.
parent 713551bc
......@@ -1405,9 +1405,9 @@ find_busiest_group(struct sched_domain *sd, int this_cpu,
for_each_cpu_mask(i, tmp) {
/* Bias balancing toward cpus of our domain */
if (local_group) {
if (local_group)
load = get_high_cpu_load(i);
} else
else
load = get_low_cpu_load(i);
nr_cpus++;
......@@ -1427,8 +1427,7 @@ find_busiest_group(struct sched_domain *sd, int this_cpu,
this_load = avg_load;
this = group;
goto nextgroup;
}
if (avg_load > max_load) {
} else if (avg_load > max_load) {
max_load = avg_load;
busiest = group;
}
......@@ -1441,11 +1440,9 @@ find_busiest_group(struct sched_domain *sd, int this_cpu,
avg_load = (SCHED_LOAD_SCALE * total_load) / total_pwr;
if (idle == NOT_IDLE) {
if (this_load >= avg_load ||
100*max_load <= sd->imbalance_pct*this_load)
goto out_balanced;
}
/*
* We're trying to get all the cpus to the average_load, so we don't
......@@ -1458,12 +1455,21 @@ find_busiest_group(struct sched_domain *sd, int this_cpu,
* by pulling tasks to us. Be careful of negative numbers as they'll
* appear as very large values with unsigned longs.
*/
*imbalance = (min(max_load - avg_load, avg_load - this_load) + 1) / 2;
*imbalance = min(max_load - avg_load, avg_load - this_load);
/* How much load to actually move to equalise the imbalance */
*imbalance = (*imbalance * min(busiest->cpu_power, this->cpu_power))
/ SCHED_LOAD_SCALE;
if (*imbalance <= SCHED_LOAD_SCALE/2) {
if (*imbalance < SCHED_LOAD_SCALE - 1) {
unsigned long pwr_now = 0, pwr_move = 0;
unsigned long tmp;
if (max_load - this_load >= SCHED_LOAD_SCALE*2) {
*imbalance = 1;
return busiest;
}
/*
* OK, we don't have enough imbalance to justify moving tasks,
* however we may be able to increase total CPU power used by
......@@ -1482,26 +1488,26 @@ find_busiest_group(struct sched_domain *sd, int this_cpu,
/* Amount of load we'd add */
tmp = SCHED_LOAD_SCALE*SCHED_LOAD_SCALE/this->cpu_power;
pwr_move += this->cpu_power*min(this->cpu_power, this_load + tmp);
if (max_load < tmp)
tmp = max_load;
pwr_move += this->cpu_power*min(SCHED_LOAD_SCALE, this_load + tmp);
pwr_move /= SCHED_LOAD_SCALE;
/* Move if we gain another 8th of a CPU worth of throughput */
if (pwr_move < pwr_now + SCHED_LOAD_SCALE / 8)
goto out_balanced;
*imbalance = 1;
return busiest;
}
/* How many tasks to actually move to equalise the imbalance */
*imbalance = (*imbalance * min(busiest->cpu_power, this->cpu_power))
/ SCHED_LOAD_SCALE;
/* Get rid of the scaling factor, rounding *up* as we divide */
*imbalance = (*imbalance + SCHED_LOAD_SCALE/2) / SCHED_LOAD_SCALE;
/* Get rid of the scaling factor, rounding down as we divide */
*imbalance = (*imbalance + 1) / SCHED_LOAD_SCALE;
return busiest;
out_balanced:
if (busiest && idle == NEWLY_IDLE) {
if (busiest && idle != NOT_IDLE && max_load > SCHED_LOAD_SCALE) {
*imbalance = 1;
return busiest;
}
......