Commit 811df0d6 authored by Brandon Labuschagne's avatar Brandon Labuschagne Committed by Evan Read

Add cycle analytics duration chart to docs

parent e377eec6
...@@ -153,6 +153,27 @@ A few notes: ...@@ -153,6 +153,27 @@ A few notes:
cycles, calculate their median time and the result is what the dashboard of cycles, calculate their median time and the result is what the dashboard of
Cycle Analytics is showing. Cycle Analytics is showing.
## Days to completion chart
> [Introduced](https://gitlab.com/gitlab-org/gitlab/merge_requests/21631) in GitLab 12.6.
This chart visually depicts the total number of days it takes for cycles to be completed.
This chart uses the global page filters for displaying data based on the selected
group, projects, and timeframe. In addition, specific stages can be selected
from within the chart itself.
### Enabling chart
By default, this chart is disabled for self-managed instances. To enable it, ask an
administrator with Rails console access to run the following:
```ruby
Feature.enable(:cycle_analytics_scatterplot_enabled)
```
This chart is enabled by default on GitLab.com.
## Permissions ## Permissions
The current permissions on the Project Cycle Analytics dashboard are: The current permissions on the Project Cycle Analytics dashboard are:
......